The Holder Group completed construction for technology leader Hewlett Packard at their Paramus, NJ corporate location. The project consisted of a constructing their data center, including installation of multiple Liebert units.

Construction Cost: $1,200,000
Square Footage: 15,000 sq ft
Duration: 13 weeks

Project Description:
• Construction of a 2,500 SF Data Center
• Renovation of Common and Office Areas
• Construction of a Conference Room
• Rigging and Installation of (4) 20-ton Liebert HVAC Units for Data Center