Wellmont Theater:

Theater management chose to fast track the project by engaging the services of a small, design/build contractor on a cost plus basis.  After 18 months, the project budget increased substantially from its initial $3,000,000 projection to a final cost of $8,000,000.  There were significant design problems, life safety and code infractions and a proven inability to obtain a Certificate of Occupancy. Based on an initial review, The Holder Group was engaged as Owner’s Representative to assist the contractor in completing the project.